Paving of the following Township roads is planned for 2018:

  • Cindy Lane, in its entirety, .31 mile, milling and base repairs scheduled to begin 6/19 for approximately three days. Roiad will be passable but please proceed with caution. Paving anticipated for 6/22 or 6/25 dependent on weather.
  • East Springtown Road, from Camp Washington Road to Naughright Road, .75 mile, during June. Vehicular access will be limited for one to two days for milling and paving during which time detours will be in place.
  • Old Farmers Road, beginning at East Mill Road, distance TBD, during the schools' summer recess.

Oil and Chip is planned for West Springtown Road (1.52 miles) and West Valley Brook Road (1.59 Miles). Portions of Reservoir, Frog Hollow and Tall Timber will also be oil and chipped.

The County plans to pave East Mill Road from Schooley's Mountain Road to East Valley Brook Road, 2.4 miles, in August or September, exact date TBD. 

 